State Government | Maharashtra - India | PID: 202469
|
The Mumbai Metropolitan Region Development Authority (MMRDA) has floated a tender for development works for car depot at Dongri for Metro Line- 9 of Mumbai Metro Rail project
The scope of work includes depot land development works and construction of depot infrastructure comprising stabling yard, operation control centre, depot control centre, administrative building, maintenance, and inspection buildings, auxiliary substation, road, underground utility duct, architectural finishing, plumbing and PEB works
The contract, worth Rs 626.69 crore, has a completion time period of 52 months (including monsoon)
The bid submission deadline is 12 March, 2024
| Updated on: 09 - Feb - 2024
|
|
|